CB 9 Series
Administrator Guide
12 CB 9 Series Installation Instructions
1.0 FOUNDATION – (see Anchor Bolt Installation Instructions)
2.0 SET THE UNIT
2.1 Screw one set of nuts and washers onto the anchor boltsAfter the foundation has
set, screw one set of nuts followed by one set of washers onto the anchor bolts. Set the
nuts such that the lowest washer is about 2½ inches above the concrete and at an even
height. To accomplish this, use a small level and check all three directions. These nuts
are not adjustable after the unit is in place. The bottom edge of the Code Blue unit will be
½-inch above the concrete when installed.
IMPORTANT: The leveling of the bottom nuts is crucial to the leveling of the unit. A small
error in the adjustment of these will be magnied after installation.
IMPORTANT: A ½-inch air gap is required between the foundation and the unit. Moisture
problems may result if this condition is not complied with.
2.2 Set the unit on the anchor boltsAlign the phone plate in the desired direction and lift
the Code Blue unit over the anchor bolts. Note that the unit weighs 190-420 pounds. Use
appropriate lifting materials and methods to avoid possible injury and/or damage.
2.3 Secure the unitAccess the mounting studs through the door on the side of the unit.
Place the second washer and nut and then tighten the mounting nuts onto the anchor
bolts. This may be more convenient if a long socket, extension and universal joint is used
to tighten the hardware.
3.0 WIRING
3.1 Ground – The ground (green) wire should be stripped and fastened to the supplied ground-
ing lug.
3.2 24V AC supply – Using the proper crimping tool, attach a #8 fork to each of the incoming
power wires and fasten them to the terminal screws labeled “Line” and “Neutral.”
3.3 120/240V AC supply – Using the proper crimping tool, attach a #8 fork to each of the in-
coming power wires and fasten them to the correct terminals as labeled on the transformer.
After completing the wire connections, install the supplied terminal covers.
See diagrams next page
All wiring must be installed and connected by experienced and certied personnel to meet
local and national electrical codes, and will include a service disconnect.